Dominion plans to build nearly 200 giant wind turbines off Virginia. But getting that energy into the grid won’t be easy.

This Orsted-owned offshore wind turbine in the North Sea is similar to what would be built off Virginia Beach if a partnership between the Danish company and Dominion Energy is successful.

The 188 giant wind turbines that Dominion Energy plans to plant 27 miles off the Virginia Beach shore will be the utility’s biggest project since its nuclear plants went online in the 1970s — but all that energy won’t do much good if it doesn’t reach customers, says Kevin Curtis, the company’s vice president-electric transmission.

Curtis knows where the submarine cables from the windfarm will come onto land — at Camp Pendleton, the state’s military reservation. He knows the nearest place to connect to the 500 kilovolt lines that form the trunk of Dominion’s grid, the Fentress substation in Chesapeake.

Advertisement

And through the spring, he and his colleagues will be working on how to get electricity — enough to power 660,000 homes — from the one point to the other.

Dominion executives have been meeting with city officials in Virginia Beach and Chesapeake as well as with the Nature Conservancy, as they try to get to know the neighborhoods, natural areas and wildlife, historic and tribal sites as well as existing rights of way in the broad corridor between Camp Pendleton and Fentress, said Ed Baine, Dominion Energy Virginia’s president. The company also will hold two community meetings, on March 2 and March 4.

Advertisement

“You really find out a lot when you just sit back and listen ... things to avoid or some opportunistic paths that we might not have recognized. It’s places to avoid and places to go,” Curtis said.

Part of what Dominion does know is that it will run underground lines from Camp Pendleton to a new substation at Oceana Naval Air Station.

But going underground with high voltage lines is costly, and so is repairing them.So the route from Oceana to Fentress will be overhead. The plan is for three 230 kilovolt lines, strung on the tall, six-armed concrete poles that carry other such lines around the region.

Dominion wants to use as many existing rights of way and as much other infrastructure as possible.

One thing the utility has already picked up from talking to Virginia Beach officials is that the planned but never built Southeast Parkway and Greenbelt that would have connected Dam Neck with Battlefield Boulevard near Chesapeake Regional Medical Center, might be a potential route for much of the line, Baine said.

Dominion aims to research and come up with preferred route and alternatives over the summer, and ask the State Corporation Commission for permission to go ahead later this year.

At the same time, because the overall project requires permits from the Army Corps of Engineers and the federal Bureau of Ocean Energy Management, a full Environmental Impact Statement is required, with a draft due next year.

Inside Business

Weekdays

Business news for the Hampton Roads region

The March 2 and March 4 meetings with be virtual. Dominion has mailed invitations to 50,000 households in Virginia Beach and Chesapeake. To participate, you can scan the QR code on the card or visit coastalvawind.com or call 1-844-319-2065.

Advertisement

Dave Ress, 757-247-4535, dress@dailypress.com